Migration
This section provides the framework for evaluating and executing AEM Edge Delivery Services (EDS) site migrations onto RHEA — the Reusable High-Efficiency Edge Architecture block library.
A repeatable, phase-based approach for taking a site from candidate validation through to a live, measurably faster EDS implementation built with RHEA blocks.
The Four Phases
| Phase | Name | Focus | Timeline |
|---|---|---|---|
| 1 | Research | Candidate validation | 1 week |
| 2 | Discovery | Block & content audit | 1 – 2 weeks |
| 3A | Build & Author | RHEA development track | 4 weeks* |
| 3B | CDN / API / Infra | Runs in parallel with 3A | 4 weeks* |
| 4 | Validate & Optimize | Measure gains, build playbook | 1 week |
*Phase 3 is project dependent; 3A and 3B run concurrently.
When to Use This
Start with the Migration Strategy Phase 1 gating questions before committing to an EDS migration. It carries the full framework: gating plus a scored fit assessment, the block and content audit, the parallel build and infrastructure tracks, and the closing measurement pass.
The gates determine whether EDS/RHEA is the right platform at all; the scored assessment then quantifies fit and surfaces risks to carry into planning.